设计概算编制和审查服务
Preparation and Review Services for Design Estimates

Design Estimates
建设项目设计概算是确定和控制建设项目全部投资的文件,是编制固定资产投资计划、实行建设项目投资包干、签订承发包合同的依据,是签订贷款合同、项目实施全过程造价控制管理以及考核项目经济合理性的依据。

设计概算投资一般应控制在立项批准的投资控制额以内;如果设计概算值超过控制额,必须修改设计或重新立项审批;设计概算批准后不得任意修改和调整;如需修改或调整时,须经原批准部门重新审批。

The design estimate of a construction project is a key document used to determine and control the total investment of the project. It serves as the basis for preparing fixed asset investment plans, implementing lump-sum project investment control, and signing construction contracts. It also underpins loan agreements, cost control throughout the project lifecycle, and the evaluation of the project’s economic viability.

In principle, the investment reflected in the design estimate should remain within the approved investment cap established at the project approval stage. If the estimate exceeds this limit, the design must be revised or the project must undergo re-approval. Once approved, the design estimate must not be altered arbitrarily; any necessary revisions or adjustments must be re-approved by the original approving authority.

该项服务可实现的目标
Objectives of This Service

我司具有丰富的设计概算编制和审查经验,通过该项工作可促进建设单位及设计单位合理分配投资资金,加强投资计划管理;有助于合理确定和有效控制工程造价;促进概算编制单位严格执行国家有关概算的编制规定和费用标准,从而提高概算的编制质量;促进设计的技术先进性与经济合理性;通过与类似工程概算技术经济指标对比分析,考察初步设计的先进与合理程度;核定建设项目的投资规模,力求建设项目总投资准确、完整,防止任意扩大投资规模或出现漏项,从而减少投资缺口,缩小概算与预算之间的差距,避免故意压低概算投资,最后导致实际造价大幅度地突破概算;为建设项目投资提供可靠的依据;有助于提高建设项目的投资效益。

 

With extensive experience in the preparation and review of design estimates, our firm delivers services that help project owners and design institutions allocate investment funds more effectively and strengthen investment planning and management. These services support the reasonable determination and effective control of project costs, ensure compliance with national regulations and cost standards, and improve the overall quality of estimate preparation.

 

We also promote the integration of technical advancement with economic efficiency in design. Through comparative analysis with similar projects, we assess the level of advancement and rationality of preliminary designs. Our work helps define an appropriate investment scale, ensuring that total project investment is accurate and complete, while preventing arbitrary expansion or omissions. This reduces funding gaps, narrows discrepancies between estimates and budgets, and avoids the intentional underestimation of costs that can lead to significant overruns during implementation. Ultimately, our services provide a reliable basis for investment decisions and enhance the overall return on project investment.

我们的服务要点
Key Service Features

 

  • 执行科学有效的概算编制、审查程序,不高估冒算、不满打粗算,保证概算编制、审查质量。
  • 执行各相关部门颁发的各种政策性文件,保证设计概算编制、审查正确、合理。
  • 关注概算编制深度概算编制说明应针对具体项目特征进行重点阐述,大中型项目符合规定的“三级概算”,不能随意简化,编制范围及具体内容与批准项目范围及具体工程内容相一致,其他费用计列符合规定。
  • 概算编制说明应针对具体项目特征进行重点阐述,大中型项目符合规定的“三级概算”,不能随意简化,编制范围及具体内容与批准项目范围及具体工程内容相一致,其他费用计列符合规定。

  • Implement rigorous and effective procedures for estimate preparation and review, avoiding both overestimation and rough or insufficient calculations, to ensure high-quality outputs. 
  • Adhere strictly to relevant policies and regulations issued by governing authorities to ensure accuracy and compliance. 
  • Emphasize the appropriate depth of estimate preparation. Explanatory notes should address the specific characteristics of each project. Medium- and large-scale projects must comply with the required “three-tier estimate” structure and must not be simplified arbitrarily. The scope and content of the estimate must align with the approved project scope, and all additional cost items must be calculated in accordance with applicable regulations.

关注概算编制准确性
Focus on Accuracy in Estimate Preparation

  • 单位工程概算
    单位工程概算是建设项目总概算的基础,是编制、审查重点。
  • 其他费用
    严格按照国家及地方政府有关部门的相关规定计算,避免出现漏算、误算、重算,对初步设计阶段实际发生的费用(如可行性研究费)可以按实计列,使概算充分反映实际投资。

 

  • Unit Project Estimates
    Unit project estimates form the foundation of the overall project estimate and are a primary focus during preparation and review.
  • Other Costs
    All additional costs are calculated strictly in accordance with national and local regulatory requirements to avoid omissions, errors, or duplication. Costs actually incurred during the preliminary design phase (such as feasibility study expenses) may be included based on actual figures, ensuring that the estimate accurately reflects the true level of investment.